AGREEMENT BETWEEN THE GOVERNMENT OF THE SLOVAK REPUBLIC AND GOVERNMENT OF THE
REPUBLIC OF HUNGARY CONCERNING CERTAIN TEMPORARY TECHNICAL MEASURES AND DISCHARGES
IN THE DANUBE AND MOSONI BRANCH OF THE DANUBE
The Government of the Slovak Republic
and
the Government of the Republic of Hungary
have agreed as follows:
Article 1
1. Immediately following the conclusion of this Agreement, the Slovak Party
will increase the discharge of water through the intake structure at Čunovo into
the Mosoni branch of the Danube to 43 m3/s
subject to hydrological and technical conditions specified in Annex 1 to this
Agreement. This value includes the flow of water through the seepage canal on the
right side of the reservoir from Slovak territory into Hungarian territory.
2. The competent Slovak and Hungarian authorities shall take all necessary measures
on their respective territories to enable the continuous flow of the increased
discharge of water from Slovak territory into Hungarian territory.
3. The water will be distributed, on Hungarian territory, between the branch system
on the right side of the Danube, the protected area and the Mosoni branch of the
Danube.
Article 2
1. The day following the conclusion of this Agreement the discharge into the main
riverbed of the Danube below the Čunovo weir will be increased to an annual average
of 400 m3/s,
in accordance with the rules of operation contained in Annex 2 to this
Agreement. Discharges entering the main riverbed of the Danube through the
inundation weir are excluded from the average calculation.
2. During the construction of the weir pursuant to Article 3 the discharge into the
main riverbed of the Danube below the Čunovo weir will be regulated in accordance
with Annex 3 to this Agreement.
Article 3
1. There will be a weir partly overflowed by water and constructed by the Hungarian
Party in the main riverbed of the Danube, at rkm 1843. The main parameters of the
weir are specified in Annex 4 to this Agreement.
2. The Parties undertake to ensure the issuance, without delay, of the
administrative authorization required by their respective national legislation for
the construction and maintenance of the weir in accordance with this Agreement.
3. The costs of the construction and maintenance of the weir will be borne by the
Republic of Hungary.
4. The construction of the weir will begin not later that 10 days following the
conclusion of this Agreement and is anticipated to be completed within a period of
50 days from the commencement of works.
Article 4
The Parties undertake to exchange those data of their environmental monitoring
systems operating in the area that are necessary to assess the impacts of the
measures envisaged in Articles 1-3. Collected data will be regularly exchanged and
jointly and periodically -evaluated with a view to making recommendations to the
Parties. The observation sites, parameters observed, periodicity of data exchange,
the methodology and periodicity or joint assessment are contained in Annex 5 to this
Agreement.
Article 5
1. In the event that either Party believes the other Party is not complying
with this Agreement, and fail to persuade the other Party that it is in breach, the
Party may invoke the good offices of the Commission of the European Union and both
Parties agree to give close cooperation to the Experts of the Commission and to take
duly into consideration any opinion rendered by them.
2. If, for whatever reason, the good offices are not provided or are unsuccessful
and the material breach continues to exist, the Party affected will be entitled to
terminate this Agreement with a one month notice.
Article 6
This Agreement has a temporary character, pending the judgment of the International
Court of Justice in the case concerning the Gabčíkovo - Nagymaros Project and is
without prejudice to existing rights and obligations of the Parties as well as to
their respective positions in the dispute before the Court and, in any event, unless
otherwise agreed, it shall terminate 14 days after the judgment of the International
Court of Justice in the case concerning the Gabčíkovo-Nagymaros Project.
Article 7
On the termination of this Agreement and unless otherwise agreed or decided, Hungary
shall at its own expense remove the weir referred to in Article 3.
Article 8
This Agreement shall enter into force on the date of its signature.
Done at Budapest on the 19 day of April, 1995, in duplicate, in the Slovak,
Hungarian and English languages, the English text to prevail in the event of any
discrepancy.
For the Government of the Slovak Republic
|
|
For the Government of the Republic of Hungary
|
Annex No. 1
Hydrological and technical conditions for the increase of the discharges into the
Mosoni Danube
1/ The increase of the discharge into the Mosoni Danube and into the right
side seepage canal of the Hrušov reservoir from 20 m3/sec up to 43
m3/sec will be ensured subject to the following hydrological and technical conditions:
1.1 Provided that minimum difference between the water-level of the Mosoni Danube
and the Hrušov reservoir is 5.10 m.
1.2 Provided that the minimum water level of the Hrušov reservoir is 130.40 m
above sea level.
1.3 Provided that the water-level of the Mosoni Danube does not exceed 125.30 m
above sea level.
1.4 Provided that the entrances to the intake structure are unobstructed.
Whenever the discharges of the Danube exceed 4000 m3/sec
(involving the inundation of the flood-plain), the water-borne materials will
move to a greater extent this may restrict the amount of water which can be
provided.
1.5 Provided that there is no failure in the electricity network system. If the
network system is damaged or in the event of any other failure of the generating
capacity, the energy system will turn off automatically and the capacity of the
intake structure will be reduced to halt of the original.
2/ At the request of the Hungarian party the Slovak Party will moderate the
discharge for a period specified by the Hungarian party.
3/ The selected site for the measuring of the discharge of the Mosoni Danube
is a gauge at 0.160 km on the left bank of the canal on the territory of the Slovak
Republic. The selected site for the measuring of the discharge of the right side
canal of the Hrušov reservoir is on the regulating weir at 1.100 km on the
territory of the Hungarian Republic.
Annex No. 2
Rules of operation
The volume of water discharged through the Čunovo weir into the main river bed of
the Danube to correspond to the annual average of 400 m3/sec.
The annual average discharge in Bratislava corresponds to 2025 m3/sec.
The annual average discharge into the main Danube river bed in each specific
year will correspond to the formula:
where :
- VDevín is the average yearly discharge in the Devin profile in
the specific year.
- V Danube is the average yearly discharge to the main Danube river
bed in the specific year.
- During the growing season the discharge into the main river bed will be higher
than during the dormant season.
- The discharge into the main river bed of the Danube will correspond to actual
discharges in the Devin profile.
- The discharges released through the inundation weir during flood will not be
included in the calculation.
The discharges in the Devin profile together with the corresponding discharges at
the Čunovo weir.
January
February March
April
May
June
600 250
600 250 600 250
600 400 600 400
600 400
2200 250 2000 250
1500 250 1100 400
700 400 700 400
2300 251 2100 258
1600 250 1200 400
800 400 800 400
2400 273 2200 280
1700 271 1300 400
900 400 900 400
2500 295 2300 301
1800 392 1400 400
1000 400 1000 418
2600 317 2400 323
1900 314 1500 400
1100 400 1100 440
2700 339 2500 345
2000 336 1600 400
1200 400 1200 462
2800 360 2600 367
2100 358 1700 400
1300 440 1300 483
2900 382 2700 389
2200 380 1800 400
1400 405 1400 505
3000 404 2800 410
2300 401 1900 414
1500 427 1500 527
3100 426 2900 432
2400 423 2000 436
1600 449 1600 549
3200 448 3000 454
2500 445 2100 458
1700 471 1700 571
3300 469 3100 476
2600 467 2200 480
1800 592 1800 592
3400 591 3200 498
2700 489 2300 501
1900 514 1900 600
3500 513 3300 519
2800 510 2400 523
2000 536 4600 600
3600 535 3400 541
2900 532 2500 545
2100 558
3700 557 3500 563
3000 554 2600 567
2200 580
3800 578 3600 585
3100 576 2700 589
2344 600
3900 600 3700 600
3200 600 2800 600
4600 600
4600 600 4600 600
4600 600 4600 600
July
August
September Október
November December
600 400
600 400 600 250
600 250 600 250
600 250
700 400
900 400 1100 250 1500
250 1800 250 2000 250
800 400
1000 400 1200 262 1600
250 1900 264 2100 258
900 400
1100 400 1300 283 1700
271 2000 286 2200 280
1000 400 1200 400
1400 305 1800 292
2100 308 2300 301
1100 400 1300 400
1500 327 1900 314
2200 330 2400 323
1200 400 1400 400
1600 349 2000 336
2300 351 2500 345
1300 400 1500 400
1700 371 2100 358
2400 373 2600 367
1400 405 1600 400
1800 392 2200 380
2500 395 2700 389
1500 427 1700 421
1900 414 2300 401
2600 417 2800 410
1600 449 1800 442
2000 436 2400 423
2700 439 2900 432
1700 471 1900 464
2100 458 2500 445
2800 460 3000 454
1800 492 2000 486
2200 480 2600 467
2900 482 3100 476
1900 514 2100 508
2300 501 2700 489
3000 504 3200 498
2000 536 2200 530
2400 523 2800 510
3100 526 3300 519
2100 558 2300 551
2500 545 2900 532
3200 548 3400 541
2200 580 2400 573
2600 567 3000 554
3300 569 3500 563
2300 600 2500 595
2700 589 3100 576
3400 591 3600 585
4600 600 2600 600
2800 600 3200 600
3500 600 3700 600
4600 600 4600 600
4600 600 4600 600
4600 600
The capacity of the by-pass weir when open under conditions of a minimum water level
in the reservoir (which is 128.2 m above sea level), is 290 m3/sec. The
discharge of 400 m3/s can be assured under the condition that the water
level in the reservoir is 128.45 m above sea level, and 600 m3/sec under
conditions of a water level of 129.05 m above sea level.
The water level in the reservoir is lowered only when required for construction or
reparation works or when the discharge in Devin is below 925 m3/s.
The possible differences in discharges which will be ascertained through monitoring
by 31 Oct. will be adjusted within the shortest possible period by the end of the
same year so that the average of 400 m3/sec is attained.
The changes in the discharges through the Čunovo weir will occur at intervals of
200 m3/sec. measured at the Devin site. Thus for instance at 800, 1000, 1200,
1400 ... 2000, 2200 m3/sec.
This distribution of the water resources shall be in force for 1995 and will be
adjusted before the 1996 growing season on the basis of the results of a joint
evaluation of the monitoring.
Annex No. 3
Annex No. 4
* Main parameters of the weir to be constructed at rkm 1843 of the Danube
1. The weir which is partly overflowed by water will be constructed at rkm 1843 of
the Danube.
2. Main parameters of the weir:
width between banks
300 m
width of the crest
5 m
width of the overflowed section
100 m
height of the center point of the
overflowed section
121. 80 B. s .1.
gradient of the downstream slope
1 : 10
gradient of the upstream slope
1 : 3
3. The elevation of the weir crest will be established in such a way that at the
discharge of 600 m3/s,
the backwater at rkm 1851.7 of the Danube and elevation of 124.00 Bsl would not
exceed.
4. The water level regulation at rkm 1843 take place when the discharge of the
Danube is between 250-1300 m3/s.
5. A maximum quantity of 150 m3/s
will be discharged into the right side branch, system on the Hungarian side.
* Based on the documentation approved under the number
No. VOD 161/A 28/1993-V
No. 21.663/17/1993
Annex No. 5
Matters relating to monitoring of environmental impacts
Monitoring is divided into the following monitoring items:
Monitoring of surface water levels and discharges
the Danube:
profile at Devin
profile at Medveďov
profile at Komárno - Komárom
profile at Štúrovo - Fsztergom
profile at Rajka
profile at Dobrohosť
profile at Dunaremete
profile downstream and upstream of overflowed weir at rkm 1843, (water level only)
Reservoir at Čunovo and the Danube downstream and upstream of the by-pass weir
(water level only)
Reservoir at Gabčíkovo (water level only)
Tailrace canal downstream of Gabčíkovo (water level only)
Malý Danube:
at Bratislava
at Trstice
Mosoni Duna:
downstream of the intake structure at Čunovo
at Mecsér
at Győr
Structures at Rajka
Seepage canal at Čunovo (on the Slovak territory)
No. 1. Lock of the outlet
No. 2. Lock of the water level control
No. 6. Lock of the water level control - Mosoni Duna
No. 1. Lock of the side branch Kiliti - Cikolai, Zátonyi Duna
No. 5. Lock at the seepage canal
Frequency of measurements: continuous on a daily basis
Monitoring of surface water quality
the Danube:
upstream Bratislava *
at Dobrohosť
at Gabčíkovo
at Medved'ov *
at Gönyű
at Komárno - Komárom
at Štúrovo – Esztergom
Reservoir, bypass canal, seepage canals, river branches:
- upper part of the reservoir at Rusovce *
- the reservoir at Kalinkovo (left and right side)
- downstream of Mosoni Danube the intake structure
- the profile at Šamorín (left, middle and right side)
- the power canal at the ferry station
- the tailwater canal downstream of Gabčíkovo *
- the seepage canal at Čunovo *
- the seepage canal at Hamuliakovo
- the Mosoni Duna at Rajka
- the Mosoni Duna at Mecsér
- the Mosoni Duna at Vének
- the Malý Dunaj at Kolárovo
- the river branches Helena and Doborgaz
- the Šulianske river branch
Frequency of measurement:
- stations marked by * - 12 times per year, between the 10th and 20th of each
month,
- all other stations in: January, March, April, May, June, July, September,
November, between the 10th and 20th of each month.
List of parameters:
- temperature, pH value, conductivity at 25°C, O2
- cations: Li, Na, K, Ca, NH4, Mn, Mg, Fe
- anions: HC03, Cl, S04, N03, N02, P04, P
- trace elements: Hg, Zn, As, Cu, Pb, Cr, Cd, Ni, Vanadium
- COD, BOD, dissolved materials (mineralization)
- biological parameters: Saprobility index, bioseston, chlorophyll,
- number of algae, zooplancton, macrobenthos, according to the decision of the
monitoring group,
- microbiological parameters, coliform bacteria, mezophilic bacteria,
psychrophilic bacteria
- organic matters, TOC, Nonpolar extractable - UV, - IR, EOX, AOX, phenols,
humic acids,
- organic micropollutants, polyaromatic hydrocarbons, - polychlorobiphenyls
(and others, to be agreed)
Sediments:
- at jointly selected stations, e.g. at places of surface water quality
sampling,
- three places in the Slovak and three in the Hungarian flood plain
Extent of parameters:
granulometric curves, organic matters and other selected parameters
Frequency of measurement: once per year in autumn
Monitoring of ground water levels
Monitoring of ground water levels will be carried out on wells between the Malý
Danube and the Lajta - Mosoni Danube. Wells to be chosen in profiles based on maps
containing all observation wells. [At least at 150 wells on the Slovak territory and
at least at 100 wells on the Hungarian territory to be chosen.]
Frequency of measurement: once per week
Monitoring of ground water quality
Ground water quality will be monitored on the municipal water supply [and ground
water] wells between the Malý Danube and the Lajta - Mosoni Danube, [at least 10
localities on each territory. In addition to this other at least 10 selected ground
water quality wells on each territory] should be monitored. These wells should be
those which satisfy hygiene criteria for drinking water wells and sampling should be
commonly agreed.
Frequency of measurement: once per month.
Quality should be evaluated according to the standards for drinking water in force
in both countries.
Monitoring of soil moisture (aeration zone)
[At least 10] monitoring areas to be selected on each territory from among the
localities already monitored.
Frequency of measurement: once every 10 days, but in winter (November, December,
January and February) twice a month. Each locality should also include a ground
water level monitoring well.
Monitoring of biota:
- microbenthos and macrobenthos in the Danube and river branches at places of
water level measurements
- fish, in all surface waters
- [Forestry, on at least 8 selected places from among existing monitoring
localities on each side]
- Special water related organisms as for example: Odonata, Ephemeroptera,
Trichopetra, Braconidea and others, jointly selected.
Special monitoring
For the estimation of the impact of the overflowed weir special monitoring to be
carried out. This will include measurements of flow velocities, water levels, water
quality, micro and macro benthos, sediments, ground water quality in the impounded
reach etc.
Submitting of data and reports:
Both sides will use data jointly agreed and will use jointly agreed methods of
evaluation. All monitoring items and locations, and methods of measurements to be
jointly agreed. Annual reports will include only measured data in tabulated,
graphical and map forms with short explanations.
Joint and verification measurements will be carried out at any location where a
discrepance occurs.
Data exchange will be carried out at three month intervals. Annual reports to be
submitted as joint reports by the end of each calendar year and covering a period or
a hydrological year.
Annual reports will be issued in English language with standardised graphical
annexes in Hungarian or Slovak languages.
Statute
Monitoring will be carried out in accordance with the Statute of nominated
Monitoring Agents.
Statute will be prepared by: Ing. Árpád Kovács, Ministry of Environment
(Hungary), Ing. Dominik Kocinger, Government plenipotentiary for the GNP (Slovakia)
Draft statute will be prepared jointly following the signing of this document and
before 31. May 1995.
Text in square brackets [] contains Slovak proposals subject to agreement by the
Monitoring Agents.
|